State Route 133 Sewer Expansion – 2019

Stauffer Site Services LLC completed the State Route 133 Sewer Expansion project. The project consisted of the installation of 8″ diameter PVC gravity sewer lines, a pump station and a force main on State Route 133 to expand the sewer infrastructure from Main Street north to the interchange at State Route 32. The Village secured $250,000 in Appalachian Regional Commission grant funds and $150,000 through Clermont County Community Development Block grant funds for the project. Please call (513) 724-6107 with any questions about the project.

Todds Run Foster Sewer Project – 2019

Stauffer Site Services LLC completed the Todds Run Foster Sewer Project. The project consisted of the installation of 8″ diameter PVC gravity sewer line from the Todds Run Foster Lift Station on Todds Run Foster Road.  Please call (513) 724-6107 with any questions about the project.

 

Gay St. Reconstruction Phase I – 2020

Fillmore Construction has been awarded the contract for the Gay St. Reconstruction Phase I project.  In general, the project consists of the complete reconstruction of approximately 1,300 feet of Gay Street from N. Front Street to Fourth Street. Storm sewer, sanitary sewer and water main will be replaced and new curbing installed.

The road will be reconstructed to 37′ curb to curb. The storm sewer and water line will be replaced through the entirety of the project with sanitary sewer being replaced from 2nd Street to Fourth Street. Existing curb ramps will be replaced with ADA complaint ones. The Village secured $500,000 in Small Government grant funds for the project.   This project is complete.

Broadway and 4th St. Sidewalk Project – 2021-22

The project consists of the removing and replacing sidewalk, driveway aprons and improving the drainage on parts of 4th Street and Broadway Street. Additional details will be available soon. The Village secured $125,368.20 in Clermont County Development Block grant funds for the project.  Please call (513) 724-6107 with any questions about the project. This project is complete.

Gay St. Reconstruction Phase II – 2021-22

The project consists of the complete reconstruction of Gay Street from Fourth Street to the Railroad.  Welsh Excavation Inc. has been awarded the contact for Gay Street Reconstruction Phase II.  Additional details will be available soon.  The Village secured $588,868 in Ohio Public Works grant funds for the project.  This project is complete.

Sewer Lining – Wilmar Ave. and West Main St. – 2022

The project involves cleaning and televising existing sewers and laterals, sewer and lateral lining, and point repairs together with the necessary appertaining work. This project is complete.

2023 Road Resurfacing

Curry Drive

Kermit Avenue

Mulberry Alley

2nd Street

New Community Park Entrance 2022

The reconfigured entrance to the community park was completed in 2022. The location provides better sight lines to crossing traffic as well as an additional turn lane for smoother and safer traffic flow. The village secured $20,000 in Clermont County Parks grant money for the project.

Old US 32 Water Line Replacement 2022-2023

The project will include replacing 4,644 feet of water main, 6 hydrants, 12 gate valves and 32 water service lines. The project will include 8 service lines directional drilled and one 8-inch water main directional drilled under Old SR 32. Gate valves and tee’s will be installed at each intersection. The existing 6-inch water main will be abandoned in place. The village secured $513,562 in grant funding from the Ohio Public Works Commission for the project.

E Main Street Sidewalk – Community Park to Intersection of SR 133 and E Main St. 2023-2024

The project consists of the installation of a 12ft. wide shared use path from the bridge on E Main Street to the intersection of SR 133 and E Main Street. The Village secured $389,238 in Transportation Alternative grant funds from Ohio, Kentucky, Indiana Regional Council of Governments (OKI) Please call (513) 724-6107 with any questions about the project. INFO LINK

Broadway/Sixth Street Water Main Replacement and Sidewalk Addition 2023-2024

This project replaces water mains on Broadway from Gay Street to the dead end and Sixth Street between Main and Spring Streets. The Sixth Street portion also included a 4ft. widening of the street with an installation of a 5ft. sidewalk with curbs and gutters. The village secured $267,720 in grant funding from the Ohio Public Works Commission for the project

Water Tower Improvements 2023

This project involves the painting and repairing of both the 200,000 gallon 8th Street and 300,000 gallon East Main Street water towers. The village secured $508,350 in grant funding from the Ohio Public Works Commission for the project.

Gay St. Reconstruction Phase III – TBD

The project consists of the complete reconstruction of Gay Street from the Railroad to High Street. The project is currently in the design phase. Additional details will be available soon.  Please call (513) 724-6107 with any questions about the project.